If 30 men can do a piece of work in11days-work in9 hours daily, how many hours a day 55men have to work in order to finish another piece of work thrice as great in 18 days 
Asked by aswinkumarak8912655 | 30 Oct, 2019, 01:22: PM
answered-by-expert Expert Answer
30 men can do a piece of work in 11 days working 9 hours
To complete the work, 30 men needs 11 x 9 = 99 hours
1 men can do the work in 99 x 30 = 2970 hrs
1 men require 297 x 3 = 8910 hrs to finish thrice the work
55 men can do thrice the work in 8910/55 = 162 hours
Since the work is completed in 18 days
So, 55 men have to work 162/18 = 9 hours a day
Answered by Renu Varma | 31 Oct, 2019, 10:05: AM
CBSE 10 - Maths
Asked by biswajitgope404 | 09 May, 2024, 09:30: PM
ANSWERED BY EXPERT ANSWERED BY EXPERT
CBSE 10 - Maths
Asked by vishalgunjan13 | 09 May, 2024, 02:13: PM
ANSWERED BY EXPERT ANSWERED BY EXPERT
CBSE 10 - Maths
Asked by mukammilh19 | 07 May, 2024, 02:28: PM
ANSWERED BY EXPERT ANSWERED BY EXPERT
CBSE 10 - Maths
Asked by laxman44verma | 01 May, 2024, 09:46: PM
ANSWERED BY EXPERT ANSWERED BY EXPERT
CBSE 10 - Maths
Asked by dagardisha39 | 28 Apr, 2024, 12:58: PM
ANSWERED BY EXPERT ANSWERED BY EXPERT
CBSE 10 - Maths
Asked by raopaidi | 25 Apr, 2024, 04:06: PM
ANSWERED BY EXPERT ANSWERED BY EXPERT
CBSE 10 - Maths
Asked by aditikaldate7 | 21 Apr, 2024, 03:16: PM
ANSWERED BY EXPERT ANSWERED BY EXPERT
CBSE 10 - Maths
Asked by rrajansinghakb199 | 08 Apr, 2024, 05:12: PM
ANSWERED BY EXPERT ANSWERED BY EXPERT
Get Latest Study Material for Academic year 24-25 Click here
×