A contractor with a work force of 420mens can complete a work of construction of a building in nine months. Due to request by the owners he was asked to complete the job in seven months. How many extra men he must employ to complete the job?
Asked by narenderrohila75 | 16 Sep, 2018, 08:24: PM
answered-by-expert Expert Answer
 
 

Let a be the extra number of men employed to complete the work in 7 months.
Number of men   420      a
Months                 9        7
As we know,
the number of men hired and the time required to finish the piece of work are inversely proportional.
Therefore, 
420 × 9 = a × 7
a = 540
Thefefore, the number of extra men required to complete the job in 7 months = 540 - 420 = 120
Answered by Yasmeen Khan | 17 Sep, 2018, 02:43: PM
CBSE 8 - Maths
Asked by sarkarchaitali4001 | 02 May, 2024, 04:11: PM
ANSWERED BY EXPERT ANSWERED BY EXPERT
CBSE 8 - Maths
Asked by jaiswal445512 | 01 May, 2024, 05:42: AM
ANSWERED BY EXPERT ANSWERED BY EXPERT
CBSE 8 - Maths
Asked by jigmetyangchen13 | 28 Apr, 2024, 02:33: PM
ANSWERED BY EXPERT ANSWERED BY EXPERT
CBSE 8 - Maths
Asked by kalpana3821 | 28 Apr, 2024, 06:48: AM
ANSWERED BY EXPERT ANSWERED BY EXPERT
CBSE 8 - Maths
Asked by chauhannaman12b | 25 Apr, 2024, 09:33: PM
ANSWERED BY EXPERT ANSWERED BY EXPERT
CBSE 8 - Maths
Asked by gk9941740 | 23 Apr, 2024, 05:13: PM
ANSWERED BY EXPERT ANSWERED BY EXPERT
CBSE 8 - Maths
Asked by pinkiyadav79919 | 22 Apr, 2024, 08:03: PM
ANSWERED BY EXPERT ANSWERED BY EXPERT
CBSE 8 - Maths
Asked by kaminiverma8787 | 16 Apr, 2024, 04:22: PM
ANSWERED BY EXPERT ANSWERED BY EXPERT
Get Latest Study Material for Academic year 24-25 Click here
×