A group of men decided to do a job in 8 days. But since 10 men dropped out after 1st day, 2 more men dropped out after 2nd day, 2 more men dropped out after 3rd day and so on, the job got completed at the end of 12th day. How many men were there at the beginning?   55     56     57     58
Asked by 105236 | 31 Aug, 2021, 06:26: PM
answered-by-expert Expert Answer
Let x men in group . If work is to be completed in 8 days , then number of man-days = 8x
 
Man-days in each day is tabulated below 
 
day 1 2 3 4 5 6 7 8 9 10 11 12
Man-day x x-10 x-12 x-14 x-16 x-18 x-20 x-22 x-24 x-26 x-28 x-30
 
sum of man-days , 8x = x +(x-10) + (x-12) + (x-14) + (x-16) + (x-18) + (x-20) + (x-22) + (x-24) + (x-26) + (x-28) +(x-30)
 
8x = 12 x  - ( 10 + 12+ 14 ...................... +28+30 )
 
8x = 12 x - [ (11/2) ( 10 + 30 ) ] = 12 x - 220 
 
From above expression, we get , x = 55 
 
Hence , there were initially 55 men in the group
 

Answered by Thiyagarajan K | 16 Sep, 2021, 11:37: PM
CBSE 10 - Maths
Asked by kumarrishavsingh7 | 17 Oct, 2023, 12:37: AM
ANSWERED BY EXPERT ANSWERED BY EXPERT
CBSE 10 - Maths
Asked by dixitayush414 | 04 Jan, 2023, 09:03: PM
ANSWERED BY EXPERT ANSWERED BY EXPERT
CBSE 10 - Maths
Asked by apal63216 | 02 Jan, 2021, 07:40: PM
ANSWERED BY EXPERT ANSWERED BY EXPERT
CBSE 10 - Maths
Asked by arindeep.singh | 10 Jul, 2020, 06:33: PM
ANSWERED BY EXPERT ANSWERED BY EXPERT
CBSE 10 - Maths
Asked by pushpa.Kudle09 | 12 Mar, 2020, 12:37: AM
ANSWERED BY EXPERT ANSWERED BY EXPERT
CBSE 10 - Maths
Asked by dastirthankar13 | 10 Mar, 2020, 08:22: PM
ANSWERED BY EXPERT ANSWERED BY EXPERT
CBSE 10 - Maths
Asked by drhimasingh | 26 Dec, 2019, 06:14: PM
ANSWERED BY EXPERT ANSWERED BY EXPERT
Get Latest Study Material for Academic year 24-25 Click here
×