Let x men in group . If work is to be completed in 8 days , then number of man-days = 8x
Man-days in each day is tabulated below
day | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Man-day | x | x-10 | x-12 | x-14 | x-16 | x-18 | x-20 | x-22 | x-24 | x-26 | x-28 | x-30 |
sum of man-days , 8x = x +(x-10) + (x-12) + (x-14) + (x-16) + (x-18) + (x-20) + (x-22) + (x-24) + (x-26) + (x-28) +(x-30)
8x = 12 x - ( 10 + 12+ 14 ...................... +28+30 )
8x = 12 x - [ (11/2) ( 10 + 30 ) ] = 12 x - 220
From above expression, we get , x = 55
Hence , there were initially 55 men in the group
Answered by Thiyagarajan K | 16 Sep, 2021, 11:37: PM
Application Videos
Concept Videos
CBSE 10 - Maths
Asked by kumarrishavsingh7 | 17 Oct, 2023, 12:37: AM
ANSWERED BY EXPERT
CBSE 10 - Maths
Asked by Dilkhushmohad055 | 28 Dec, 2022, 11:02: AM
ANSWERED BY EXPERT
CBSE 10 - Maths
Asked by 105236 | 31 Aug, 2021, 06:26: PM
ANSWERED BY EXPERT
CBSE 10 - Maths
Asked by apal63216 | 02 Jan, 2021, 07:40: PM
ANSWERED BY EXPERT
CBSE 10 - Maths
Asked by arindeep.singh | 10 Jul, 2020, 06:33: PM
ANSWERED BY EXPERT
CBSE 10 - Maths
Asked by pushpa.Kudle09 | 12 Mar, 2020, 12:37: AM
ANSWERED BY EXPERT
CBSE 10 - Maths
Asked by dastirthankar13 | 10 Mar, 2020, 08:22: PM
ANSWERED BY EXPERT
CBSE 10 - Maths
Asked by drhimasingh | 26 Dec, 2019, 06:20: PM
ANSWERED BY EXPERT
CBSE 10 - Maths
Asked by drhimasingh | 26 Dec, 2019, 06:14: PM
ANSWERED BY EXPERT