90 persons can dig a well in 40 days. After they have worked for 10 days, how many more persons Should be employed to complete the work in another 20 days
Asked by Pammiprasad150 | 17 Nov, 2018, 01:27: PM
Expert Answer
number of persons working = 90
number of days required to complete = 40
hence the work requirement = 90×40 = 3600 man-day
90 persons worked for 10 days, hence completed work = 90×10 = 900 man-day
Remaining work = 3600 - 900 = 2700 man-day
if remaining work has to be completed in 20days, then required persons = 2700 / 20 = 135
Answered by Thiyagarajan K | 17 Nov, 2018, 09:36: PM
Application Videos
Concept Videos
CBSE 9 - Maths
Asked by kulkarniridima6 | 09 May, 2024, 05:30: PM
ANSWERED BY EXPERT
CBSE 9 - Maths
Asked by rathorgaurav2945 | 21 Apr, 2024, 10:31: PM
ANSWERED BY EXPERT
CBSE 9 - Maths
Asked by monika.vns14 | 18 Apr, 2024, 05:15: PM
ANSWERED BY EXPERT
CBSE 9 - Maths
Asked by gulshanelectronics2017 | 15 Apr, 2024, 05:35: PM
ANSWERED BY EXPERT
CBSE 9 - Maths
Asked by tripura78839 | 12 Apr, 2024, 09:05: PM
ANSWERED BY EXPERT
CBSE 9 - Maths
Asked by singhanjali0199 | 12 Apr, 2024, 08:29: PM
ANSWERED BY EXPERT
CBSE 9 - Maths
Asked by killerstealer593 | 11 Apr, 2024, 07:50: PM
ANSWERED BY EXPERT
CBSE 9 - Maths
Asked by saee.shinde3069 | 31 Mar, 2024, 10:12: PM
ANSWERED BY EXPERT
CBSE 9 - Maths
Asked by rathoreraj7296 | 31 Mar, 2024, 08:09: PM
ANSWERED BY EXPERT