175 man can a canal 3150m long in 36 days how many men are required to dig a Canonl 3900 m long in 24 days|
Asked by abhivantepaka2412 | 09 Nov, 2018, 08:56: PM
Expert Answer
If 175 men can dig a canal which is 3150 m long in 30 days.
let a man digs x m daily.
By equation,
x m * 175 Men * 36 Days = 3150 m
Solving which gives x as 0.5 m
It means each man will dig 0.5 m daily.
By the same equation,
0.5 m * no. of Men * 24 Days = 3900 m
Solving which gives no. of men as 325 Men
Hence 325 Men are required to dig a canal of 3900 m working for 24 days.