JEE Class main Answered
30 men complete work in 16 days how many men can complete work in 20 days?
Asked by atul_rclal | 25 Dec, 2018, 09:59: PM
Expert Answer
30 men complete a work in 16 days
the total amount of work = 30×16 man days
now the work needs to be completed in 20 days
20×x = 30×16
x=24
24 men can complete work in 20 days
Answered by Arun | 26 Dec, 2018, 09:30: AM