Sunil takes 5 days more than Anil to complete a certain work.4 Days after starting the work, Anil left the work .The remaining work done by Sunil in 5 days. Find how many days each will take to complete the work.  
Asked by gauravkakuste12340 | 22 Nov, 2019, 01:12: PM
answered-by-expert Expert Answer
Sunil takes 5 days more than Anil to complete a certain work.4 Days after starting the work, Anil left the work .The remaining work done by Sunil in 5 days.
So Anil takes 10 days and Sunil takes 15 days
Answered by Arun | 26 Nov, 2019, 09:39: AM
CBSE 10 - Maths
Asked by aditikaldate7 | 21 Apr, 2024, 03:16: PM
ANSWERED BY EXPERT ANSWERED BY EXPERT
CBSE 10 - Maths
Asked by rrajansinghakb199 | 08 Apr, 2024, 05:12: PM
ANSWERED BY EXPERT ANSWERED BY EXPERT
CBSE 10 - Maths
Asked by nagalaxmidurgarao937 | 08 Apr, 2024, 01:42: PM
ANSWERED BY EXPERT ANSWERED BY EXPERT
CBSE 10 - Maths
Asked by sonawnerohan01 | 23 Mar, 2024, 12:25: PM
ANSWERED BY EXPERT ANSWERED BY EXPERT
CBSE 10 - Maths
Asked by pathakvaishnavi9139 | 23 Mar, 2024, 10:45: AM
ANSWERED BY EXPERT ANSWERED BY EXPERT
Get Latest Study Material for Academic year 24-25 Click here
×