if 49 men can dig a well 28 m deep in 52 days how many men will be required to dig a well 40 m deep in 35 days
Asked by srmahale1 | 07 Nov, 2019, 04:14: PM
answered-by-expert Expert Answer
28m deep well can be dug in 52 days by 49 men
1m deep can be dug in 52 days by 49/28 = 7/4 men
1m deep can be dun in 1 day by 7/4 x 52 = 91 men
40m deep can be dug in 1 day by 91 x 40 = 3640 men
40m deep can be dug in 35 days by 3640/35 = 104 men
Answered by Renu Varma | 08 Nov, 2019, 10:24: AM