90 men complete the work in 24 days if they work 8 hrs/day
 
total work hours for 90 men  = 24×8 = 192 hours
 
number of man-hours to complete the work = 90×192
 
if work has to be completed in 18 days with begin mathsize 12px style 7 1 half end style working hours, total work hours 18×begin mathsize 12px style 7 1 half end style = 15×9 = 135 hours
required number of workers = (90×192) / 135  =  128