Karan , Kabir , kartik can together finish a project in 4 dys . Karan by himself can do it in 12 days & Kabir can do himself by 10 days. how many days will kartik take to finish the project alone?
question image
Asked by dasgudi144 | 18 Dec, 2022, 01:55: PM
answered-by-expert Expert Answer
Question:
Karan , Kabir , kartik can together finish a project in 4 dys . Karan by himself can do it in 12 days & Kabir can do himself by 10 days. how many days will kartik take to finish the project alone?
To solve such problems, calculate the work done in 1 day when they work together and then calculate the work done in 1 day by each individual. At the end equate the two results and get the required unknowns.
The solution is as follows:
Hence, takes 15 days to finish the project alone.
Answered by Renu Varma | 19 Dec, 2022, 10:52: AM
CBSE 10 - Maths
Asked by yogitamanojkumar | 09 Jan, 2023, 04:01: PM
ANSWERED BY EXPERT ANSWERED BY EXPERT
CBSE 10 - Maths
Asked by ramugirija9496 | 10 Jan, 2021, 07:44: PM
ANSWERED BY EXPERT ANSWERED BY EXPERT
CBSE 10 - Maths
Asked by arajeevshashank | 25 Jun, 2020, 11:12: AM
ANSWERED BY EXPERT ANSWERED BY EXPERT
CBSE 10 - Maths
Asked by arajeevshashank | 10 Jun, 2020, 06:14: PM
ANSWERED BY EXPERT ANSWERED BY EXPERT
Get Latest Study Material for Academic year 24-25 Click here
×