If A, B andd C working separately can complete a work in 11 days , 20 days and 55 days respectively , then how soon can the work be done if A is assisted by B and C on alternate days ?
Asked by Sanjay | 28th Mar, 2017, 12:45: PM
Expert Answer:
Hence, 8 days are required.
Answered by Rebecca Fernandes | 28th Mar, 2017, 08:09: PM