CBSE Class 8 Answered
A can finish a job in 12 days while B can finish the same job in 15 days. How much time will they take, if both A and B work together?
Asked by Topperlearning User | 04 Jun, 2014, 01:23: PM
Expert Answer
A can finish the job in 12 days.
Therefore, in 1 day A can finish part of work.
B can finish the job in 15 days.
Therefore, in 1 day B can finish part of work.
If they work together,
In 1 day they will complete, part of work.
Now
Thus, both will complete the work in days that is days.
Answered by | 04 Jun, 2014, 03:23: PM
Application Videos
Concept Videos
CBSE 8 - Maths
Asked by mmanju10984 | 19 Jan, 2024, 06:29: PM
ANSWERED BY EXPERT
CBSE 8 - Maths
Asked by sd9854849 | 07 Jan, 2024, 08:09: AM
ANSWERED BY EXPERT
CBSE 8 - Maths
Asked by mishramanisha242 | 20 May, 2022, 07:48: PM
ANSWERED BY EXPERT
CBSE 8 - Maths
Asked by chehakkataria2006 | 02 Mar, 2020, 03:40: PM
ANSWERED BY EXPERT
CBSE 8 - Maths
Asked by kaustubhkladda | 09 Feb, 2020, 12:12: PM
ANSWERED BY EXPERT
CBSE 8 - Maths
Asked by acanilchauhan7 | 05 Nov, 2019, 11:50: PM
ANSWERED BY EXPERT
CBSE 8 - Maths
Asked by 365542180671386 | 16 Dec, 2018, 03:44: PM
ANSWERED BY EXPERT
CBSE 8 - Maths
Asked by Topperlearning User | 04 Jun, 2014, 01:23: PM
ANSWERED BY EXPERT
CBSE 8 - Maths
Asked by Topperlearning User | 04 Jun, 2014, 01:23: PM
ANSWERED BY EXPERT
CBSE 8 - Maths
Asked by Topperlearning User | 04 Jun, 2014, 01:23: PM
ANSWERED BY EXPERT