A and B can finish a piece of work in 30 days, B and C in 40 days while C and A in 60 days. A, B, C
together will finish the work in how many days?
Asked by rhinithaa | 31 Jul, 2010, 03:42: PM
Dear Student,
(A + B)'s one day's work = 1/30
(B + C)'s one day's work = 1/40
(C + A)'s one day's work = 1/60
Adding we get
2(A + B + C)'s one day's work =
(A + B + C)'s one day's work = 3/80
So together A, B and C can do the work in 80/3 days
Regards,
Team Topper Learning
Answered by | 31 Jul, 2010, 07:18: PM
Application Videos
Concept Videos
CBSE 10 - Maths
Asked by prassanna.j | 10 Sep, 2023, 08:42: PM
CBSE 10 - Maths
Asked by bhaveskumar9938 | 08 Jul, 2023, 05:40: AM
CBSE 10 - Maths
Asked by ruchipandey20071978 | 11 May, 2023, 06:55: AM
CBSE 10 - Maths
Asked by choithanimahak | 05 Aug, 2022, 09:06: PM
CBSE 10 - Maths
Asked by anuragchoudhary812 | 19 Jul, 2022, 07:00: PM
CBSE 10 - Maths
Asked by patelnaimesh842004 | 17 Jul, 2022, 09:05: PM
CBSE 10 - Maths
Asked by patelnaimesh842004 | 17 Jul, 2022, 07:43: PM
CBSE 10 - Maths
Asked by shreeram091984 | 17 Jul, 2022, 08:17: AM